d/b
constructors completed their 24th project for TU Electric, a three-story
administration/warehouse building at Comanche Peak in Glen Rose, Texas. This
facility contains 120,000 square feet and was completed within 180 calendar
days, even though storm damage in September delayed the project for three weeks.
d/b constructors worked closely with GSBS Batenhorst Architects and Frank Neal
and Associates Engineers to provide a total engineered package, including all
mechanical trades, in minimum time.
d/b constructors has almost $5 million in completed
construction for TU Electric and TXU since 1988.